Behro Consulting Engineers, as project MC in all aspects of supply, installation and commissioning of equipment and facilities, has played a key role in leading and supervising this project.

Behro's services in electrical and mechanical systems in this project include trains, power supply systems, signaling, telecommunications, control and ventilation for stations and tunnels, BAS, fire alarm and extinguishing equipment, as well as depot and parking equipment. The telecommunication system includes data transmission subsystems, radio telecommunications, clock system, PA and CCTV.

Project Description

Tehran Metro Line 4, about 22 km long, starts from Kolahdooz station located on Doran highway in the southeast of Tehran and passes through Piroozi street (several stations) and Enghelab street (stations such as Darvazeh Dowlat and Theatr-E Shahr) and after passing Towhid, Shadman, Dr. Habibollah and Ostad Moin stations in Azadi street, arrives at Azadi Square (Tehran West Terminal) and after passing Ekbatan Town, reaches Eram-e Sabz Station on Line 5 (Tehran-Karaj metro line). Extension to Mehrabad Airport, with length of about 3 km, includes 3 stations, 4 LPS and one RS substation. The western extension of this line to the Janatabad area with length of about 4 km with 3 stations is under construction.

Line 4 includes 19 underground stations including 5 intersection stations and 3 high voltage substations (HVS). The line also includes 15 RS substations, 48 LPS substations, one depot and parking near R4 station in Afsariyeh area, and one parking lot near A4-3 station in Ekbatan area. Control center of this line is located in the existing control center building.

The capacity (PPHPD) of this line is 45,000 with a headway of two minutes. One of the special features of this line is construction of island platforms in Eram-e Sabz and Kolahdooz stations, where passengers on both routes use the same platform to get on and off the trains.

tehram metro line 4 plot

Project specification

Item

Description

Length

22 km

No. of stations

19 (underground)

Length of platform

160 m

No. of HVS

3

No. of parking and depots

2

PPHPD

45000

Headway

2 minutes

Intersection with other lines

5 intersections (with 1, 2, 3, 6 & 7)

Stations Characteristics

Code

Name

Location

Status

A4-7

---

Chahar Bagh Square, Janat Abad

Under Construction

A4-6

---

Kashani – Janat Abad intesection

Under Construction

A4-5

---

North Parvaneh – Hakim highway intersection, west ferdows

Under Construction

A4-4

Eram-e Sabz (Ekbatan)

Ekbatan town, phase 2

Being Operated

A4-3

Ekbatan Town

Ekbatan town, phase 2

Being Operated

A4-2

Bimeh

2nd bimeh street, Lashgari highway

Being Operated

A4

Meydan-e Azadi

Rahmani highway, Azadi square

Being Operated

B4

Ostad Moein

Azadi street, Next to Ostad Moein intersection

Being Operated

C4

Doctor Habib-o-llah

Azadi street, near Habib-o-llah intersection

Being Operated

D4H2

Shademan

Azadi street, between Behboodi and Shademan intersections

Being Operated

E4

Towhid

Azadi – Navad intersection

Being Operated

F4

Meydan-e Enghelab-e Eslami

Enghelab-e Eslami square

Being Operated

G4I3

Teatr-e Shahr

Valiasr junction

Being Operated

I4

Ferdowsi

Ferdowsi square

Being Operated

K1J4

Darvazeh Dowlat

Saadi – Mofatteh intersection, Enghelab street

Being Operated

P2K4

Darvazeh Shemiran

Ebn-e Sina square

Being Operated

M4

Meydan-e Shohada

17 Shahrivar – Piroozi junction

Being Operated

N4

Ebn-e Sina

Piroozi street, next to Imam Ali highway

Being Operated

O4

Piroozi

Poormand alley, Piroozi street

Being Operated

P4

Nabard

Nabard junction , Piroozi street

Being Operated

Q4

Nirooye Havaei

Proozi street, between 4th and 5th Niroo Havayi streets

Being Operated

R4

Shahid Kolahdooz

Dowran highway

Being Operated

---

Mehrabad Airport Terminal 1&2  

Mehrabad Airport Terminal 1&2

Being Operated

---

Mehrabad Airport Terminal 4&6

Mehrabad Airport Terminal 4&6

Being Operated


Share to